Atlas Offices

Project — Commercial

Atlas Offices

Frankfurt, Germany

Project dossier

Client
Atlas Verwaltung GmbH
Location
Frankfurt, Germany
Industry
Commercial
Scope
Workplace and breakout furniture for 3 floors + acoustic wall panels and reception surfaces
Scale
Headquarters, 9,000 m², 620 staff
Status
Delivered 2025
Delivery timeline
RFQ to final floor: 26 weeks
Cost band
USD 780K–980K
Sample data

Designed by

Raumplan Collective

Procured by

Atlas Verwaltung GmbH

Owner / operator

Atlas Verwaltung GmbH

Overcoming challenges

The brief, and how we landed it

The challenge

After tender, the client's board cut the furniture budget by 24% without changing the design intent. The three floors handed over eight weeks apart, but the client's team needed the first floor occupied before the old lease expired. German workplace standards required documented fire and emissions compliance for every panel and textile.

How we delivered

We ran a structured VE exercise with the design team, holding the visual spec while re-engineering construction across 11 product types. Production was phased to the floor handovers, with each wave pre-staged and QC'd as complete floor kits. All panels shipped with EN 13501 fire classifications and emissions documentation compiled for the client's compliance file.

Scope of supply

What left our loading dock

Supply list

  • Breakout and lounge furniture for 3 floors, 340 pieces
  • Acoustic wall panels in 4 standard modules, EN 13501 documented
  • Reception desk and wall cladding in sintered stone
  • Meeting-room tables, 26 units
  • Floor-kit packing with phased delivery waves and compliance file

Materials used

  • Textiles
  • Oak
  • Metal
  • Cement
  • Glass

Value engineering on this project

The VE exercise recovered 21% of the 24% budget cut: sofa frames moved from hardwood to engineered beech with no change to upholstery appearance, and reception cladding swapped solid surfacing for large-format sintered stone. Acoustic panels were standardised to two module sizes, cutting panel variants from 14 to 4. Phased floor-kit deliveries removed the client's quoted cost for a temporary off-site warehouse.

The pieces

Supplied from our lines

Planning something similar?

Share the drawings and the budget frame — we will show you exactly how we would build it.